Skip to main content

Budgets and publishing

Labour is the largest controllable cost for most hospitality operators. StaffBrik's budgeting tools give you visibility into planned wage spend as you build the rota, so you can make informed decisions before shifts are published and committed.

Setting a week's budget​

Budgets are set per location, per week, from the rota itself. When a week has no budget, the rota shows a Budget not set banner with a Set budget button. Once a budget is set, use Adjust next to it in the rota header to change it.

Both open the Set weekly budget dialog, which asks for two things:

  • Estimated net revenue - what you expect to take that week, ex VAT. Choose Daily entry to give a figure for each day, or Weekly entry to give one total that is split evenly across the week. Copy previous week's budget fills in last week's figures as a starting point.
  • Target wage % - the share of that revenue you want to spend on labour. It starts at your organisation default from StaffBrik Settings.

Example: A cafe expecting £8,000 of net revenue with a target of 30% has a labour budget of £2,400 for the week.

SettingValue
Estimated net revenue£8,000
Target wage %30%
Weekly budget£2,400

Save budget saves the forecast, the daily split and the target together, in one go. The dialog stays open until the save has gone through, and if it fails it says so and keeps your figures, so you can try again without retyping anything. You never end up with a new forecast and the old target, or the other way round. Closing the dialog with figures you haven't saved asks "Discard your changes?" first.

If you change the target in this dialog, owners and admins are asked whether to make it the new default as well. The question only appears when you changed the target this time, not every time you save a week whose target differs from the default. Members save the target for that week only, because the default is an organisation setting.

tip

A percentage target scales naturally with trade. A quiet January week and a busy December week have different revenue, and should have different staff budgets. Using Daily entry also gives each day its own budget, which makes Wage % by day far more useful.

The budget​

The weekly budget is your estimated net revenue multiplied by your target wage %. It is what appears on the rota as your spending target. The planned shifts are what is compared against it: the planned cost less its holiday pay and SSP, which are cash the week pays out but need no cover. The planned cost itself, holiday pay and SSP included, stays the headline, with its own standing against the budget shown beside it.

Planned and actual labour​

StaffBrik keeps two labour figures for every rota week, and it helps to know which is which.

  • Planned is every shift on the rota, drafts included, with a shift covered by leave swapped for the SSP or holiday pay that replaces it. It is the cash the week pays out, and the headline figure on the rota page and the dashboard, because you want to know where the week stands while you are still planning, not after you publish. The budget itself is judged on the planned shifts alone, with the holiday pay and SSP shown beside the figure rather than counted against staffing (see Budget tracking on the rota).
  • Actual labour is what was worked. Once a day is over, anyone who clocked in and out that day is costed from their clock-ins, so an early finish, a late one or someone who came in to help without a shift all count. Anyone who did not clock in is costed from their published shifts; today and the days ahead use published shifts too. Draft shifts are a plan, not labour, so a rota with nothing published and nobody clocked in has no actual labour yet. Actual labour is what the actual wage % on the rota, and the Weekly wage, Employee costs and Day analysis reports, are built on.
tip

If your team does not clock in with StaffBrik, actual labour is your published rota. Update the rota when someone goes home early or an extra pair of hands comes in, and the reports follow.

Both figures treat leave the same way. A shift covered by a logged absence or by approved time off is taken out, and what you pay for that day is counted instead:

  • Sickness - that day's Statutory Sick Pay, on the absence's qualifying days only, and only until SSP stops at the 28-week maximum. SSP is never charged on a day that is paid as holiday, so a sick day kept as holiday is charged once, as holiday.
  • Holiday and other paid time off - priced day by day at the employee's base hourly rate in force on that day, which is what their holiday pay costs you. A day that falls on a scheduled shift pays that shift's own paid time (after its own break); other days follow your break policy.

Employer NI and pension are added on top of both, once, in the same way as for shifts. A shift covered by leave adds nothing to the week's NI and pension.

When you log an absence, any shift you untick as not affected counts as worked, and keeps its cost on the rota. See Logging absences.

Open shifts that nobody has claimed have no cost until someone takes them.

Example: A rota has £2,000 of published shifts and £300 of draft shifts. One published £80 shift is covered by approved holiday. The holiday pay for that day, at the employee's base hourly rate with employer NI and pension added, comes to £76.

How each person's week is costed​

Employer NI and pension are worked out on each person's whole week, the way payroll does it:

  • One threshold a week, across every site. Someone working at two of your sites in one week gets one £96 NI threshold and one £120 pension threshold for the week, not one per site. When their shifts change at one site, the other site's rota totals update too.
  • Starters are charged in their first week. A new starter whose first day is mid-week is charged employer NI and pension in that first rota week.
  • Salaried staff are costed up to their weekly hours. The hours they work over them, less paid leave that week, are costed by their Extra hours setting, which can be nothing. A short week is costed on its rota hours. See How a salaried week is costed.
  • Rolled-up holiday is in the rota cost. For staff whose pay rate rolls holiday into the hourly cost (zero-hours and casual staff, by default), each shift includes 12.07% holiday pay, plus the NI and pension on it. Their holiday is paid as they work, so the time off they book is not charged again. See Zero-hours and casual staff.
PlannedActual labour
Shifts£2,300£2,000
Covered by leave-£80-£80
Paid time off, with NI and pension+£76+£76
Total£2,296£1,996

Budget tracking on the rota​

The budget tracker sits at the top of the week view:

What you seeWhat it shows
BudgetThe week's budget
TargetThe target wage % behind it
HoursHours scheduled this week. Open shifts nobody has claimed, and ones that expired unclaimed, are not counted
% of budgetThe planned shifts as a share of the budget, shown on the bar. In a week with holiday pay or SSP the label reads "of budget, on shifts"
PlannedThe planned cost for the week, drafts included: the cash it pays out. In a week with leave pay, the split follows it, for example "£1,266.68 on shifts + £215.20 holiday pay"
Remaining or over budgetHow much is left, or how far over the shifts are. When the leave pay takes the cash past the budget, that is shown underneath, for example "£341.88 over in cash"

Holiday pay and SSP are cash paid out in that week (an August full of holidays really does cost more), so they stay in the planned figure and are never stripped out of it. But a holiday needs no cover, so it is not overstaffing: the budget, the colour of the bar and the forecast % are judged on the shifts alone. A week with no leave pay reads exactly as it always has.

The bar changes colour as the plan fills the budget:

  • Green - at or under budget.
  • Amber, with one arrow - over budget by up to 10% of it, for a £1,000 budget up to and including £1,100.
  • Red, with two arrows - more than 10% over.

These are the same bands as Wage % by day. The comparison is made in pence, so a penny over is over: under the figure the tracker says Over budget or Well over budget, even when the % rounds to 100%. The wage % beside the bar (actual or forecast) is judged against your target wage % with the wage % rule, not by the budget's colour, so a week can be on budget and over its target.

When the week has open shifts, the tracker adds what they would cost if they were claimed, for example "Projected if open shifts claimed +£120.00", and says when that would take the week over budget: Would be over budget (amber) or Would be well over budget (red). Viewers don't see this line, because it is priced at each role's hourly rate. They still see the planned shift total and its budget band, and both leave unclaimed open shifts out. Owners, admins and members also see the Employment Allowance figures, which viewers don't.

Before you have recorded any takings, the planned shifts are also shown as a share of your forecast, for example "(31% of forecast)". In a week with leave pay the label says so, "(44% of forecast on shifts)", with the cash share beside it, "52% in cash". Once takings are recorded, the tracker shows your actual wage % instead (see Budget vs actual).

info

Budget tracking is a planning tool, not a hard block. StaffBrik will not prevent you from scheduling shifts that push you over budget - it trusts you to make the right call. Sometimes a busy weekend justifies going over target. The point is that you make that decision consciously, not accidentally.

Wage % by day​

Below the rota grid, Wage % by day shows each day's staff cost as a share of its takings, on one scale, with a dashed line at your target wage %. A bar's height, its colour and the figure above it all show the same number:

  • Green - at or under your target.
  • Amber, with one arrow under the bar - over your target by up to 10% of it (for a 35% target, up to and including 38.5%).
  • Red, with two arrows under the bar - more than 10% over it.

The arrows let you tell amber from red without relying on colour, and a line under the chart says what they mean. The week figures in the footer carry the same arrows. The Wage % card on Home draws the same chart with the same rule, and so does the Day analysis report.

Solid bars are days with takings recorded, showing your actual wage %. Dashed bars are the other days: the planned cost, or the worked cost once the day has ended, against that day's forecast. Under each day you see its staff cost, its takings (forecast takings in italics) and its hours. In a week with any, a Holiday row and an SSP row follow, with that day's leave pay, so the reason for a high day is in view. A tag says where the staff cost comes from:

  • Clocked - everyone who worked clocked in and out, so the cost is what they actually worked.
  • Part clocked - some staff clocked in; the rest are costed from their published shifts.
  • Rota - nobody clocked in, so the cost is the published shifts.
  • Forecast - no takings recorded yet, so the % is against the forecast.
  • No cover - a closed day whose only cost is holiday pay or SSP: nobody was on the rota, and nobody was needed.

A day nobody was on the rota for and nobody worked reads Closed instead of a bar, even if a few sales came in that day, so a shut day never shows as 0.0%. Holiday or sickness on such a day still reads Closed, tagged No cover, when the day's forecast is £0 or it is a closed date in Settings > Locations: the pay is cash the week pays out, but it needed no cover, so it is not overstaffing and does not count as a day over target. A day that reads Closed is also left out of the day count in "Over target on 2 of 6 days", so the count always matches the days the chart shows. The week's wage % still includes any leave pay or stray sales from that day, because they are real money. A day with holiday or SSP on it, a forecast left in, nobody on the rota and no closed date shows its wage % as usual, since the site expects trade with nobody in. A day in a week you are still planning reads Closed too until you add a shift. It is only a label: the week's figures in the footer don't change.

The footer gives the week so far: Actual so far (the recorded days' staff cost as a share of their takings), Projected week (those days plus the forecast for the rest) and how many recorded days went over target. Once the week has ended with takings in for every day, Actual so far becomes Weekly wage %: the whole week's staff cost as a share of its takings. In a week with holiday pay or SSP, each of these also gives the shifts' share, for example "Forecast week 52.0% · 44.4% on shifts". A day with staff cost but £0 takings counts as over target. If a day with staff on it has neither takings nor a forecast, there is no projection, rather than one that quietly leaves that day out.

This helps you spot imbalances - for instance, if Thursday's wage % is disproportionately high because you over-staffed for a quiet lunch. Clocked hours also catch the drift a rota cannot see: 15 minutes past the end of a shift for four people is an extra hour of pay.

Hover over a day, or tab to it, to see the full detail: the day's forecast takings and, once they are in, its actual takings, the day's wage budget, what was taken out for absence or time off, what was added back (SSP, with NI and pension and Paid time off, with NI and pension) and, on a day with leave pay that is not reading Closed, its cost on shifts alone. A closed day with only leave pay on it explains instead that the pay needed no cover. The Day view and the All locations day cards show the same planned figures as the week's day columns, and the week grid's Daily total row names the holiday pay or SSP inside a day's total.

Hovering over the weekly cost on a person's row explains that it shows their leave at pay. Employer NI and pension on leave are added in the day totals.

DayStaff costTakingsWage %
Monday£310£80038.8%
Wednesday£380£1,10034.5%
Saturday£560£2,20025.5%

In this example, Saturday costs the most in staff, but for the trade it does it is the most efficient day. Monday costs far less, yet is over a 35% target: the same four people on a quiet day. Looking at cost alone would point you at the wrong day.

tip

Use Wage % by day to match staffing to expected trade. A restaurant that does 40% of its weekly revenue on Friday and Saturday should expect to spend a proportionate amount on labour those days. Flat staffing across every day is a common source of waste.

The Employment Allowance on the rota​

If you've told StaffBrik you claim the Employment Allowance, it comes off the week's labour cost, pay day by pay day, until it's used up. It keeps to the same split as the budget:

  • Cash figures take off the whole allowance: the planned cost, holiday pay and SSP included, and the wage % worked out from it, the actual wage % once takings are in, and each day's wage % in Wage % by day.
  • A wage % on shifts takes off only the allowance on the shifts' own employer NI. The part that covers the NI on holiday pay and SSP is set aside along with the leave pay, so the figure still reads your staffing.
  • The budget stays at the full cost, on shifts (see below).

Each wage % after the allowance shows the figure before it alongside whenever the two differ. In a week with no holiday pay or SSP, the planned cost is all shifts, so the cash and on-shifts figures are the same.

Example: a week with a £10,000 forecast, a £3,000 budget, £2,800 of planned shifts and £300 of holiday pay. The week's allowance is £240, of which £216 covers the NI on the shifts and £24 the NI on the holiday pay.

Before the allowanceAfter it
Planned, holiday pay included£3,100£2,860
Wage % of forecast, in cash31%29%
Planned shifts£2,800£2,584
Wage % of forecast, on shifts28%26%
% of budget93%93%

In a week the allowance applies to:

  • The budget tracker adds a line under the planned cost: "Labour cost £3,100.00, Employment Allowance −£240.00, after allowance £2,860.00". Before takings are in, the share of your forecast reads "(26% of forecast on shifts) (28% before the allowance)", with the cash share beside it, "29% in cash (31% before the allowance)". Once takings are in, the actual wage % is after the allowance on that labour, for example "Actual wage 27% of net revenue (29% before the allowance)", and the forecast beside it is the share on shifts: "Forecast: 26% on shifts (28% before the allowance)".
  • Wage % by day adds an Allowance row under Staff, with each day's share of the allowance. Each day's wage %, bar and colour are after it. Hovering over a day adds lines such as "Employment Allowance: −£25.00", "After the allowance: £285.00" and "Wage %: 38.8% before the allowance", and on a day with holiday pay or SSP, On shifts alone adds the figure after the shifts' allowance, for example "On shifts alone: £230.00, after the allowance £212.00". In the footer, the week figures are after the whole allowance and their "on shifts" figures after the shifts' part, each followed by the figure before the allowance, for example "Forecast week 28.6%, 31.0% before the allowance · 25.8% on shifts, 28.0% before the allowance". Part-way through a week, the count of days comes first: "Actual so far (2 days) 31.3%, 32.9% before the allowance".
  • The All locations view adds the same line to each site's card, under its Planned cost (and under the holiday pay and SSP split, when there is one): "Labour cost £3,100.00, Employment Allowance −£240.00, after allowance £2,860.00". The card's Wage % of forecast (or Wage % of forecast, on shifts, in a week with leave pay) is after the allowance on its shifts, with the figure before it underneath.
  • The StaffBrik dashboard's wage cost card and This week card add "Employment Allowance −£240.00, after allowance £2,860.00" under the week's planned cost. On the combined card for all your sites, and a site you pick from it, a week with no holiday pay or SSP leads with the cost, for example "Labour cost £2,400.00, Employment Allowance −£150.00, after allowance £2,250.00". Their budget % stays at the full cost.

Viewers see the rota and the dashboard at the full cost, without these lines.

The budget isn't affected. The % of budget, the colour of the bar, remaining, over budget, the "over in cash" line and the over-budget alerts are all judged at the full cost, before the allowance, and the tracker says so: "Budget is checked before the Employment Allowance." So a week can show a wage % under target and still be over budget. That keeps the budget meaning the same thing all year, including after the allowance runs out. Shift costs, and each person's weekly cost on the rota, keep employer NI in too: the allowance belongs to the week's total.

In the week the allowance runs out, the figure after it steps up to the full cost, because from then on you pay employer NI in full. Owners and admins see why in a line under the tracker's allowance figures that week, for example "The Employment Allowance runs out with the 12 Sep pay day. From then employer NI is paid in full, so the figure after the allowance steps up."

Weeks still ahead use the rota you've planned, so their allowance is an estimate that firms up as the days are worked. Owners and admins can see what's left of the allowance, and when it runs out, on the StaffBrik dashboard.

Over-budget alerts​

When the planned shifts go over the budget, StaffBrik makes it clear:

  • The budget tracker turns amber (red when more than 10% over) and shows the overspend, for example "£280 over budget".
  • A panel appears under the tracker, showing what the overspend would cost if it were repeated every week. It says Over budget. in amber, or Well over budget. in red when the week is more than 10% over, with one arrow or two.
  • The StaffBrik dashboard and Home raise an alert such as "Planned shifts are £280.00 over budget (112% of budget planned)", marked urgent when the week is more than 10% over, and the site's card in the All locations view shows Over budget (amber) or Well over budget (red) for that site.
  • On the StaffBrik dashboard, the budget bar and the wage cost card use the same bands, with Over budget or Well over budget in words. On All locations they judge the combined planned shifts against the combined budget, so one site over budget doesn't make the whole business read as over.

These all judge the planned shifts, drafts included and leave pay aside, so the warning arrives while you can still change the plan, and a week of holidays never raises one on its own. They are judged at the full cost, before any Employment Allowance, too. The Weekly wage report keeps the cash view: its actual cost and variance include the holiday pay and SSP, as your payroll will.

A week with a £0 budget (a £0 forecast) reads as having no budget. It never shows an overspend, an Over budget badge in the All locations view, or a dashboard over-budget alert. Nor does a closed site.

You are not prevented from publishing - the alert is advisory. The goal is to ensure over-budget weeks are intentional, not accidental.

Publishing rotas​

Rotas follow a two-stage workflow: draft and published.

Draft stage​

Shifts you add with Save as draft, and the shifts you copy from a previous week, start in draft status:

  • Draft shifts show on the rota in StaffBrik, but not in the Team App.
  • Employees see nothing - their rota appears blank until you publish.
  • You can freely add, edit, move, and delete shifts without triggering notifications.
  • The budget tracker is fully active during draft, so you can optimise before committing.

This is your planning phase. Take as long as you need.

Where the week stands​

For one site, the week's header shows where the rota stands, beside the week. On a phone, the Day view shows the same line under the view buttons. All locations shows no line.

  • No shifts yet - the week has no shifts.
  • Draft, not published - the week has shifts, and none has been published.
  • Published Tue 17 Nov by Sam - when the week was last published, and who published it. "Published just now" for the first minute. The name shows only when that was a publish of the whole week. Publishing one shift with Save & publish moves the date on, without a name. Some older weeks show a plain Published, with no date or name.
  • 3 changes not published - beside Published, the drafts still to publish. Changes you save to shifts that are already published are not counted: staff see them as soon as you save them.

Publishing​

When the rota is ready, click Publish in the toolbar. It shows how many drafts there are, for example Publish (12), and Publish changes (3) once the week has been published before. The publish window shows what is about to happen before anything changes:

  • The first publish of a week reads "Publish the Riverside rota?" with the week and how many shifts and people it covers. A later publish reads "Publish 3 changes to Riverside?" and lists each draft it will publish. Changes you already saved to published shifts are not in the list: staff already see them, and were told when you saved them.
  • Tell staff is on each time the window opens. With it on, each person whose shifts this publish adds gets one Team App message with their week, for example "Your rota for w/c Sat 21 Nov is out: 3 shifts, 22.5h. Tap to see them.", or "Your rota has changed: new shift on Mon 23, 14:00 to 22:00." for a later publish. The window shows one person's real message, and Who will be told lists everyone. Switch it off to publish without telling anyone.
  • People who haven't set up the Team App yet are named, each with a link to print or send the rota for that person (their shifts, including the drafts you are about to publish). Brikly does not text or email it: print it or save the PDF and send it yourself. People who have switched rota notifications off in the app are counted, not named.
  • Late at night (from 21:00 to 06:59, UK time) the window says so, for example "It's 23:40. Phones will buzz now.", in case you would rather switch Tell staff off. Nothing is held back until morning.
  • Open shifts are offered either way. Tell staff covers each person's rota message. Open shifts in the publish are still offered to eligible staff with it off, so the button then reads Publish without rota messages, and late at night the window says "Open shift offers will buzz phones now."
  • A shift that has already started is never announced as new.

Publishing then:

  1. Changes all draft shifts to published status.
  2. Makes the shifts visible to each employee in the Team App, and with Tell staff on sends each person their one message.
  3. Posts any draft open shifts to staff, and sends eligible staff the "New open shift" notification, whether or not Tell staff is on.

A message then confirms it, for example "Rota published: 28 shifts for 9 people. 8 told in the Team App." An over-budget week publishes like any other.

If another manager is changing one of the drafts at that moment, the window says "Someone is changing a shift on this rota right now. Try publishing again in a moment." and stays open, so you can press Publish again. If the connection drops while publishing, the window closes and says "We couldn't confirm whether the rota was published. Check the rota before publishing again." The rota refreshes, so check it before you press Publish again.

A draft open shift that has already started, or whose claim cutoff has passed, could never be claimed, so Publish leaves it as a draft and says why, for example "1 open shift was not posted because its claim cutoff has passed. Edit it from the Open shifts row to set a later cutoff, or withdraw it." Everything else still publishes.

caution

Once published, employees can see their shifts. Changing a published shift's person, day or times tells the people it affects, unless you switch Notify off (see Changes to published shifts). While you can still make changes, frequent edits to published rotas erode staff trust - aim to get it right before you publish.

Best practice: weekly publishing rhythm​

Most hospitality operators follow a consistent rhythm:

  1. Monday or Tuesday - copy last week's rota and adjust for the coming week.
  2. Wednesday - review budget, finalise adjustments, confirm with team leads.
  3. Thursday - publish the rota for the following week.

This gives staff at least three to four days' notice of their shifts - a reasonable expectation in hospitality, and well ahead of any contractual or legal notice requirements.

tip

The earlier you publish, the fewer last-minute swap requests you will receive. Staff who know their shifts by Thursday can plan their personal lives around them, reducing no-shows and requests for changes.

One editor at a time​

Only one person can edit a site's rota for a given week at a time, so two managers never overwrite each other's changes. There is nothing to switch on: when an owner, admin or member opens a week, StaffBrik holds it for them while they work.

Anyone else who opens that week sees "[Name] is currently editing this rota. You can view but not make changes until they finish." They can look at the rota, but cannot add, move or change shifts until it is free.

The rota is free again as soon as the person editing moves to another week or site, or leaves the rota page. If their browser closes without letting go of it, or their computer goes to sleep, it is freed after five minutes. The next person's rota then becomes editable within about half a minute, without refreshing the page.

This works the same for a draft week and a published one. Weeks that have ended stay editable too, with the reminder "This week has ended. Changes may affect historical reports." A closed site's rotas are always read-only. See Closed sites.

If StaffBrik cannot reach the server to start editing, the rota stays read-only and says "This rota is read-only for now because we could not reach the server to start editing.", with a Try again button.

Multi-location budgets​

Each location has its own independent budget:

  • Set a different forecast and target percentage per site (a high-volume restaurant may run at 28% labour, while a small cafe runs at 32%).
  • Budget tracking on the rota builder applies to the currently selected location.
  • The All locations view shows a card for each site's week, with its Planned cost (the cash figure), its Wage % of forecast (the planned shifts' share) and an Over budget badge when the shifts are over. In a week with holiday pay or SSP the card reads Wage % of forecast, on shifts, with the split under the planned cost, for example "£1,266.68 on shifts + £215.20 holiday pay and SSP". The StaffBrik dashboard's wage cost and This week card label their budget % "on shifts" and show the same split.

Example: a two-site operation

LocationRevenue forecastTarget %Budget envelope
High Street Cafe£6,00032%£1,920
Station Road Restaurant£14,00028%£3,920
Combined£20,00029.2%£5,840
tip

Resist the temptation to set the same percentage across all sites. A grab-and-go cafe with a small team and fast service naturally has a different cost structure from a full-service restaurant with a brigade kitchen. Set targets that reflect each venue's operational reality.

Budget vs actual​

Budget tracking on the rota judges the planned shifts (holiday pay and SSP aside) against a budget built from your forecast revenue, with the planned cost in cash shown beside them. Once days have passed, record your actual takings so the rota can show your actual wage %: actual labour on the days with takings recorded, as a share of those takings.

The tracker reads, for example, "Actual wage 34% of net revenue". Until the whole week has takings recorded it says how many days the figure covers, such as "(revenue for 3 days)", because only those days' labour and takings are compared. A cafe closed one day a week that records six days has a complete week. Days that are over use actual labour from clock-ins where staff clocked in. If takings are recorded but nothing on the rota is published yet and nobody has clocked in, the tracker asks you to publish the rota to see the actual wage %, because there is no actual labour to compare.

See Actual revenue tracking for how to enter actual revenue from the rota builder or the dashboard.

For weekly totals across a date range, use the Weekly wage report under StaffBrik > Reports, which compares actual labour with your budgets week by week.

Together, these tools help you:

  • See your real labour cost as a percentage of actual revenue, not just forecasts.
  • Identify weeks where forecast accuracy was poor (so you can improve future estimates).
  • Spot patterns of consistent under-staffing or over-staffing relative to actual trade.
  • Build more accurate budgets over time by understanding the gap between plan and reality.